- Project implementation in compliance with CITCC/MTNN specification
- Quality management and control, Project monitoring and weekly reports and plans.
- Verification of implementation. Change management and mediation
- Ensuring strict adherence to Health, Safety and Environment rules and regulations
- End to end testing to ensure the stipulated core traffic capacity
- Liaising on behalf of client to mediate on community and regulatory issue
FY17/18 MTNN Gombe NFE, Adamawa NFE, Bauchi NFE and Plateau NFE
Client Name:
CITCC NIGERIA LIMITED / MTN Nigeria
Associated Partners:
Not specified
Project Location:
Gombe, Adamawa, Bauchi & Plateau States
Project Started:
May 2017
Project Completed:
January 2018
Project Duration:
6 months
Project Description:
Civil work, installation of optic fibre cables, End-end test of fibre cables, OADM termination, re-measurement of quantities, verification of as-built documentation and acceptance tests, project close-up and handover